|
Published: March 25, 2008 03:31 pm
Dam's "troublesome spots" hold up decision on lake levels
By BILL MARDIS, Editor Emeritus Commonwealth-Journal
Wayne County Outlook
Monticello —
Two "really troublesome" areas in seepage-plagued Wolf Creek Dam are
requiring a "lot of extra work" and have delayed a decision on the level of
Lake Cumberland this summer.
Barney Davis, chief of the Engineering and Construction Division at the
United States Army Corps of Engineers' Nashville District, declined to
project when the lake level will be determined for the upcoming tourist
season.
However, Davis did say that "... we're not talking about months ... it
will happen quickly." Speculation that the lake level would be raised 10
feet this summer was triggered late last year in a news release from
Congressman Hal Rogers, R-Somerset.
Rogers' office announced that the level would be 690 feet above sea
level‹10 feet above the target 680‹for the 2008 tourist season.
The Corps' Nashville District, however, quickly refuted this assumption,
saying no decision had been made on the lake level. They said then, and now,
that a process would begin to determine the 2008 level when the upstream
grout line is complete.
An accelerated grouting program has been underway at the dam since
January 2007. The lake was lowered 40 feet at that time to ease pressure on
Wolf Creek Dam, classified by a panel of experts as being in high risk of
failure.
Davis, during an interview with the Common-wealth Journal, reiterated
that the Corps has a process for determining the lake level based on
"completing structural improvements and behavior of the project." Corps
engineers emphasize that the foundation of the dam is stable and improving
every day.
The first step in this process to determine the lake level begins with
completion of the upstream grout line, Davis said. "Based on the geology of
the area, we don't know how many holes we will have to drill until we get
there," Davis noted. He said the problem spots in the earthen part of the
dam are about 400 feet from the concrete section and about the midway point
of the earthen structure near the curve in the road.
Davis described the areas as "really troublesome." These problems have
pushed back completion of the upstream grout curtain. Curtains of grout, a
soupy concrete mixture pumped under pressure to fill cavities in the dam,
are planned both upstream and downstream of a diaphragm wall to be inserted
in the dam. It will be the second concrete wall, longer and deeper than a
diaphragm inserted during the 1970s.
Contractually, the upstream grout curtain was to be completed February
21. "We didn't make it," said Davis, obviously because of the troublesome
spots.
Heavy rains in the Cumberland River Basin have muddied upper reaches of
the lake and raised the level nearly 10 feet above the 680-foot target
during this phase of the rehabilitation. Water is being released through the
dam at a rate of 13,740 cubic feet per second.
Wolf Creek Dam has been plagued with seepage almost since its
impoundment in 1951. Sinkholes developed in the vicinity of the electrical
grid below the dam in the late 1960s and muddy water was observed in the
tailrace. The problem then, engineers say, was much worse that the current
seepage problem, first announced in August 2005.
The rehabilitation program currently underway is scheduled to take up to
seven years at an estimated cost of $309 million.
• Click to discuss this story with other readers on our forums.
|
|