Monticello Board accepts bids for building project
SYLVIA MCGINNIS
News Reporter

The news was a little bit better for members of the Monticello

Independent Board of Education Monday evening, as they once again heard from

Joe Nance of Ross, Sinclaire and Associates, fiscal agent for the

construction project for the new school.

During their regular monthly meeting Monday, March 20, Nance informed

board members that they have received approval from the Department of

Education to move forward with the project and that funding is now in place

to cover the cost of the base bid.

This was definitely better news than the board received during last

month's meeting, when Nance advised them to wait another 30 days before

taking any action on the bids that had been submitted just to make sure that

funding would be available for the project.

It was a disappointing delay, but the board opted to take Nance's

advice. At last month's meeting they did not take any action on the bids for

the construction project but did approve the site development package so

they could get the project started.

After informing board members that they had received approval to

continue with the project and that funding was now available, Nance reviewed

the BG1 form and other handouts with the board members.

He noted that the original plans for the building includes the base bid

plus five alternates. Nance stated that the funding that is currently in

place will only cover the cost of the base bid and will not cover any of the

alternate packages.

However, he explained to board members that there is the strong

possibility that they will be receiving additional funding that will cover

the cost for most of the alternate packages. That funding is not in place

yet, and Nance indicated that they should know within the next couple of

weeks if Monticello Independent School had received the additional money.

Once they know whether or not the additional funding is available for the

project then at that point they can decide which alternate packages to

accept.

For now, Nance said the board could move forward with the base bid and

take action regarding the alternate packages at a later date, if the need

arises.

Following this discussion, the board recessed the regular meeting and

called to order the meeting of the Monticello Independent School District

Finance Corporation.

The first order of business for the Monticello Independent School

District Finance Corporation, which consists of the board members, was to

confirm officers for the entity. Ronnie Sexton serves as president of the

district finance corporation, Jack Lair acts as the vice-president, Donnie

Robison is the secretary and Glenette Hurd is the treasurer.

Once the officers for the district finance corporation were confirmed,

they voted to adopt a resolution regarding the issuance of revenue bonds and

to also adopt a resolution authorizing the issuance of qualified zone

academy bonds.

After adopting these resolutions, they adjourned the meeting of the

Monticello Independent School District Finance Corporation and returned to

the regular board meeting.

Once the regular board meeting was called back to order, the board heard

from Daryl Wheeler of Venture Contracting, Inc., the construction manager

for the project.

He provided board members with a list of all the bids they were going to

ask the board to approve. He noted that board members had already approved

the first bid last month, which was for the site development package.

After Wheeler and members of the board reviewed the bids, the board

voted to accept construction bids and purchase orders as recommended by the

const ruction manager and architect.

Then, they had to adopt two resolutions as the Monticello Independent

Board of Education, which were similar to those they had already adopted as

the Monticello Independent School District Finance Corporation. Board

members adopted a resolution authorizing the issuance of revenue bonds and

they also adopted a second resolution which authorized the issuance of

qualified zone academy bonds.

Board members questioned Wheeler about when construction crews will

actually start working on the project. He noted that they plan to start

moving dirt soon if the weather cooperates.

In other action, the board:

* approved the calendar for the 2006-2007 school year. The calendar

approved by the board has August 9 slated as the first day of school for

students, with August 7 being the opening day for faculty and August 8 set

aside as a professional development day.

* recognized three students who competed in Governor's Cup competitions.

Jarrod Ingles competed in social studies, Chelsea Cordeiro-Shaffer competed

in language arts, and Tasia York competed in areas of written composition.

Monticello Principal Johnny Chaplin noted that these students competed in

the District Governor's Cup competition, as well as Regional and State

Governor's Cup competitions.

"They've really represented Monticello well," noted Chaplin.

* approved offering college credit courses through Somerset Community

College (SCC). Monticello Independent currently has two teachers that meet

SCC's criteria and are qualified to teach a college-level class. With this

partnership, students enrolled at Monticello Independent can take a course

and receive both high school and college credit. However, students who

enroll in these classes will be required to pay tuition to SCC. The dual

credit courses Monticello plans to offer to students includes Chemistry and

English. Chaplin noted that there is a possibility that Spanish may be

offered as well.

* approved 2006-2007 tentative school council allocations.

* reviews Monticello School staffing policies.

* approved Greattinger and Crowley as auditor for the 2005-2006 school

year.

* voted to increase stipends for the volleyball head coach and assistant

coach to match the stipends of the softball head coach and assistant coach.

* heard a personnel report.

* heard a request from board member Jerry Lair that the school

contribute toward the purchase of a child-size resuscitation mat for the

Wayne County EMS. Superintendent Donnie Robison noted that this is a worthy

cause and he felt like the board could contribute to it. He asked that

members of the board wait until next month before taking any action in the

matter so he could review the school's budget and determine how much they

could contribute.